Buying Off-Plan from a Developer (Kablan) in Israel: Sale Law, Payment Schedule, Indexation
Buying an apartment that does not exist yet is the most common way to buy new in Israel, and the most tightly regulated: every shekel you pay is guaranteed by a bank or an insurer, the contract follows a model imposed by law, and delays cost the developer money. In exchange, the unpaid balance is indexed to the construction cost index, delivery takes one to five years, and the developer writes the contract in its own favour. Here is how it works, item by item, with 2026 figures.
The short answer
Buying off-plan from a kablan (developer-builder) in Israel is governed by the Sale Law (Apartments): any payment beyond 7% of the price must be covered by a bank guarantee or an insurance policy. The list price includes 18% VAT, the developer’s lawyer fee is capped at ≈ ₪5,500 + VAT, and the mas rechisha (purchase tax) is paid within 60 days of signing. The unpaid balance is indexed to the madad tshumot habniya (construction cost index), which often adds 5 to 8% on a 20/80 schedule. Expect delivery 6 to 12 months after the contractual date, with compensation owed beyond 60 days of delay, and several years before final registration in the Tabu.
The figures to remember, 2026
- Payment without a guarantee
- 7% max
- VAT included in the price
- 18%
- Developer’s lawyer (cap)
- ≈ ₪5,500 + VAT
- Delay tolerated without compensation
- 60 days
- Usual delay observed
- 6–12 months
- Purchase tax due within
- 60 days
What the Sale Law (Apartments) guarantees
The 1974 law on the assurance of apartment buyers’ investments (חוק המכר (דירות) (הבטחת השקעות)) is the backbone of an off-plan purchase. Its principle fits in one sentence: the developer may not collect more than 7% of the price without giving you security for every additional shekel. The law allows five forms of security; two dominate in practice. There is no escrow company and no title insurance: the guarantee replaces both.
| Security | What it covers | How common |
|---|---|---|
| Bank guarantee (arvut bankait) on the statutory form | Indexed refund of the sums paid if the developer does not deliver; in practice the bank rather has the project completed | The rule in bank-financed projects (liyvi bankai) |
| Insurance policy from a licensed insurer | Same cover as the bank guarantee, issued by an insurer | Common in small projects and with self-financed developers |
| Mortgage in the buyer’s favour, caution note (hearat azhara) on land free of charges, or transfer of the land share | Real securities; the caution note prevents a sale to a third party but does not guarantee completion | Rare on their own |
In practice, every payment is made by shovar (payment voucher) from a book issued by the project’s bank, into a dedicated, closed account (heshbon liyvi); the bank then issues a guarantee in your name within 14 days. A developer who asks for a “direct” wire or for cash takes you outside the law: refuse.
The guarantee covers the money, not the apartment. If the project stops, you get your indexed payments back, but not the right to buy at the same price elsewhere. That is why the strength of the developer and of its bank is checked before signing, not after: a project without bank accompaniment (liyvi bankai) deserves twice as many questions.
Payment schedules: standard, 20/80, 10/90
The payment schedule (luach tashlumim) is the most negotiable part of the contract, and the one that changes the final cost most. Three models coexist in 2026.
| Model | At signing | During construction | At delivery | Who it suits |
|---|---|---|---|---|
| Standard (by construction stage) | 15% (₪360,000) | 5 to 7 calls for funds, ≈ 60%, at site milestones | ≈ 25% | Cash buyer, or a mortgage released in stages; limited indexation because the balance shrinks fast |
| 20/80 | 20% (₪480,000) | Nothing | 80% (₪1,920,000 + indexation) | Buyer who must sell a property, wait for aliyah or arrange a loan; developer who wants to move stock |
| 10/90 | 10% (₪240,000) | Nothing | 90% + indexation | 2025-2026 offers on the last units; the 3% above the 7% is guaranteed, the rest is not yet paid |
Why do developers offer 20/80? Because their bank lends them against signed sales, not against cash collected: a 20/80 contract unlocks the construction financing and gives the buyer a cash-flow facility that replaces a discount. The trap is in the word “replaces”: an 80% balance indexed for two and a half years costs more than a 5% discount. The arithmetic is in the next section.
Three points to negotiate on the schedule, whatever the model: a financing clause (the contract falls away without penalty if the bank declines the loan within a set period), an indexation holiday on the first months or a cap, and moving the last payment to the actual handover of keys rather than to the announced delivery date.
Indexation to the construction cost index, with a worked example
The madad tshumot habniya (residential building input price index) is published monthly by the CBS, around the 15th, for the previous month. It tracks the cost of materials, labour and site equipment, not apartment prices. The contract provides that each payment not yet made is multiplied by the ratio between the index known on the payment date and the base index, usually the one known at signing. What is already paid is no longer indexed; what remains to be paid is indexed in full.
Over ten years, this index has risen by 2 to 4% a year on average, with spikes above 5% in 2022 and in 2024-2025 under the labour shortage. The prudent assumption in 2026 is 3% a year.
| Paid at signing (20%), not indexed | 480,000 ₪ |
| Balance due at delivery (80%), before indexation | 1,920,000 ₪ |
| Indexation of the balance: 1,920,000 ₪ × (1.0767 − 1) | + 147,256 ₪ |
| Balance actually paid at delivery | 2,067,256 ₪ |
| Final price of the apartment (6.1% above the contract price) | 2,547,256 ₪ |
The same apartment on a standard schedule, where the balance shrinks at each construction stage, would carry roughly half the indexation, ₪70,000 to ₪80,000. In other words, the 20/80 “costs” nearly ₪70,000 more than the standard here, and a 5% discount (₪120,000) is worth less than the full indexation of the 20/80 (147,256 ₪). Hence the right question for the developer: “what is the final price if the index runs at 3% a year?”, and the right ask: an indexation holiday, total or capped, which is worth more than a free kitchen.
Two details. If the index falls, the contract almost always sets a floor. And the mortgage does not cover indexation: the bank lends on the contract price, the uplift comes from your own funds. Test it with the mortgage calculator, down payment increased by the expected indexation.
What the price includes, and what it does not
A new apartment’s price is listed inclusive of VAT, at 18% since 1 January 2025. There is no VAT on a resale sold by a private individual: at equal price, a new build is therefore “worth” 15% less before tax, which explains part of the new-versus-resale gap detailed on the new-build or second-hand page. New immigrants get no VAT exemption on property.
- Included: the apartment as described in the technical specification, the share of land and common areas, the mamad (the reinforced safe room required in every new home), usually one parking space and a storage room if the contract names them with their number.
- Often extra: a second parking space (₪120,000 to ₪250,000 in the center), an extra storage room, utility meter connections, condominium registration fees, air conditioning in some projects.
- Developer’s lawyer: the law caps what the developer may bill you for its lawyer at about ₪5,500 + VAT (an indexed amount), or 0.5% of the price if lower. That fee covers registration, nothing else.
- Your lawyer: 0.5 to 1% + VAT, or a flat ₪8,000 to ₪15,000. This is the lawyer who defends your interests; the developer’s lawyer defends the developer’s, by definition. Role and fees are detailed on the real estate lawyer page.
The full budget, new builds included, is detailed on the closing costs page.
The contract, the technical specification, changes and upgrades
The contract is drafted by the developer, on a 40-to-80-page template that is uniform for the whole project. It cannot depart from the Sale Law, but everything that is not regulated is written in the seller’s favour: “estimated” delivery date, broad force majeure, late-payment penalties, the right to alter the common areas, indexation with no floor. A lawyer who knows the city’s developers knows which clauses move (often about ten).
The mifrat techni (technical specification) is annexed to the contract on a form imposed by the Ministry of Housing. It lists the areas (apartment, balcony, mamad, parking), the materials, the fittings, the number of sockets per room, the brand or grade of sanitary ware and tiles, and the credits (zikuy) granted if you waive an item. Read it alongside the plans: it is the only enforceable document on what you are buying, and the gap between the specification area and the brochure’s “marketing” area commonly reaches 10 to 15%. The gross vs net square metres page explains how to read those figures.
Changes and upgrades (shinuyim ve-shidrugim) are the developer’s second profit centre after parking. Moving a partition, adding a socket, choosing tiles outside the catalogue: each request is priced by the developer, often 30 to 50% above market, payable separately and within a limited window. Past a certain stage of the build, nothing can be changed. Two rules: ask for the changes price list before signing, and route change payments through the project account so they stay guaranteed.
Delays, delivery, warranty period
The contractual delivery date is rarely met. Since 2023, delays of 6 to 12 months have been the norm in large projects, under the combined effect of the labour shortage, permits and reserve call-ups. The Sale Law, amended in 2011 and tightened in 2022, frames what you can claim:
- Up to 60 days late: no compensation. That is the statutory margin, and the contract cannot freely extend it.
- Beyond 60 days: the developer owes monthly compensation equal to the rent of a comparable apartment, uplifted by 50% in the first months and then by 25%, owed retroactively from the contractual date, first 60 days included. It is paid at the end of each month of delay, not at delivery.
- Force majeure: the developer is exempt only for an event outside its control, unforeseeable at signing, and notified to you. The war was invoked for 2023-2024 delays; a contract signed after October 2023 can hardly invoke it for the same causes.
- Delivery (mesirat mafteach): handover inspection with a protocol listing the snags, occupancy certificate (tofes 4) obtained. Do not sign a blank protocol; a building inspector (₪600 to ₪1,500) pays for the visit.
- Bedek and warranty periods: the developer repairs defects reported during the bedek period (one year for most finishes, two to seven years for waterproofing, plumbing, structure), then during a three-year warranty in which the burden of proof reverses.
The overall timeline, from reservation to registration, is on the how to buy page, with a total of 1 to 5 years off-plan against 2 to 6 months for a resale.
Mortgage on an off-plan unit, purchase tax, registration
The mortgage. A bank lends on an apartment that does not exist yet, at the same ceilings as for a resale: 75% for a resident first home, 70% for a replacement home, 50% for an investor or a non-resident. It calculates on the contract price (not the indexed price), takes the Sale Law guarantee and then the built apartment as security, and pays directly into the project account against the vouchers. On a 20/80, most of the loan is released at delivery: the pre-approval can come late, but rates or your situation may have changed. Conditions from abroad are on the mortgages for non-residents page, those for new immigrants on mortgage for new olim.
Purchase tax. It is declared within 30 days and paid within 60 days of signing, on the contract price excluding future indexation, even if you move in three years later. On our 2,400,000 ₪ example:
Resident, only home
15,538 ₪- 0% up to ₪1,978,745, then 3.5% and 5%.
- Financing up to 75%.
Non-resident or investor
192,000 ₪- 8% from the first shekel.
- Reclassified as “only home” if you become a resident within 2 years.
Oleh hadash
2,106 ₪- 0% up to ₪1,978,745, 0.5% up to ₪6,055,070.
- Purchase from 1 year before to 7 years after aliyah, until 15 January 2028.
For a future oleh, buying off-plan has one precise advantage: the date that counts for the schedule is the signing date, and aliyah can follow up to a year later. The purchase tax calculator gives the amount for your price and status; the buying as a new immigrant page details the conditions.
Registration. From signing, if the land is in the Tabu, your lawyer has a hearat azhara (caution note) entered in your name. Final registration waits for the building to be registered as a condominium (bayit meshutaf), the developer’s responsibility, which commonly takes two to five years after delivery, longer on Minhal (state) land. In the meantime, you own by contract and guarantee, and you can resell by assignment (hamchaa).
The real risks, and how they are covered
- Developer insolvency. Covered by the bank guarantee or insurance on every payment beyond 7%. Not covered: payments outside the voucher system, changes paid to subcontractors, the rise in prices in the meantime. Ask to see a guarantee already issued to another buyer in the project.
- Delay. Covered by statutory compensation beyond 60 days, provided the contractual date is a date, not “the quarter of”. Keep a 12-month rent margin in your cash plan.
- Change in the zoning plan (taba). The view, the height of the neighbouring building, the planned road: none of it is guaranteed by the contract. The lawyer checks the zoning in force and the permits filed; the rest is a bet.
- Financing refused or dearer at delivery. On a 20/80, the bank does not commit two years ahead. Covered by a financing clause, a renewed pre-approval and a safety margin in your down payment. A non-resident whose situation may change is better off with a standard schedule.
New builds negotiate differently by city: plentiful and discounted in the South and in Beit Shemesh, scarce and expensive in Jerusalem where they come through pinui-binui, dominant on the Netanya seafront. Prices by city are on the real estate prices city by city page.
What changes in 2027
Purchase tax thresholds and the 0.5% oleh schedule stay frozen until 15 January 2028: an off-plan contract signed in 2027 benefits from them whatever the delivery date. 20/80 offers and indexation holidays should become scarcer as the 2024-2025 stock clears and rates edge down. As long as the labour shortage lasts, a construction index at 3% a year remains a prudent assumption. For tax once you own (rental income, capital gains, reporting in your home country), see Shekel Guide.
Frequently asked questions
Is my money protected if the developer goes bankrupt?
Yes, provided every payment beyond 7% of the price received a bank guarantee or an insurance policy under the Sale Law. If the developer fails, the guaranteeing bank refunds the sums paid (indexed) or, more often, has the project completed by another developer. Not covered: payments made outside the voucher system and the price difference if you have to buy elsewhere.
What does a 20/80 schedule really cost?
It moves 80% of the price to delivery, but that 80% is indexed to the construction cost index for the whole build. On a ₪2.4M apartment delivered in two and a half years with the index at 3% a year, indexing the balance adds about ₪147,000. A 20/80 “without indexation” is therefore worth more than a 5% discount. Always compare the final indexed price, not the list price.
Do I need my own lawyer if the developer already has one?
Yes. The developer’s lawyer represents the developer; the fee billed to the buyer is capped by law at about ₪5,500 + VAT (or 0.5% if lower) because that lawyer only handles the registration paperwork. Your lawyer reviews the contract, negotiates the schedule, the indexation, the delay penalties and the force majeure clauses, and checks the permits and the guarantee.
When is purchase tax paid on an off-plan purchase?
Within 60 days of signing the contract, even if delivery is three years away, on the contract price excluding future indexation. A non-resident pays 8% from the first shekel; a resident buying their only home 0% up to ₪1,978,745 then 3.5% and 5%; an oleh 0.5% above ₪1,978,745 until January 2028.
How much delay is “normal” and what do I get?
The contract almost always allows 60 days without compensation. Beyond that, the law requires the developer to pay monthly compensation based on the rent of a comparable apartment, uplifted (150% in the first months, 125% afterwards), owed retroactively from the contractual date. In practice, delays of 6 to 12 months have been common since 2023.
Can I get a mortgage on an apartment that does not exist yet?
Yes. The bank lends on the contract price, pays directly into the project account against the vouchers, and takes the bank guarantee as security, then the apartment itself. Same ceilings as for a resale: 75% for a resident first home, 50% for a non-resident. The indexation uplift stays on you.
How we work
Every amount, bracket and rate on this page is checked against the official source listed at the bottom and dated. When a schedule or rate changes, the page is updated within days. Our methodology.
Sources
- Sale Law (Apartments) (Assurance of Investments of Apartment Purchasers), 1974 – consolidated text (nevo.co.il)
- Ministry of Construction and Housing – rights of a new-apartment buyer, guarantees and technical specification
- Central Bureau of Statistics – residential building input price index (madad tshumot habniya)
- Kol Zchut – buying an apartment from a developer: guarantees, delivery delays, capped lawyer fee